Project Description

Consulting Engineer:
Lawler Engineers

Main Contractor:
David Flynn Ltd.

Brief Description:

The Brewhouse is a renovated buildings from the original brewery in the new Abbey Quarter. The new offices are based over two floors. The new offices included open office space, reception and staff breakout areas with enclosed offices, meeting rooms and boardrooms.

Lawler’s utilised the high ceiling by putting in a raised access floor to install an underfloor busbar system to keep cabling to a minimum, this created a very clean and easily manoeuvrable desk layout.

Our team of CM Kevin and Foreman Daniel pushed the team to complete the project on an aggressive schedule to meet the clients requirements and expectations.